How much of Germany’s electricity do data centres use?
Short answerAbout 4%.
About 4% of Germany’s gross electricity consumption in 2025, or about 21 TWh. Gross consumption is everything the country uses, including what is lost in the grid. The figure is an estimate by the Borderstep Institute, and the German government uses it in its 2026 data-centre strategy. Use has grown: the industry group Bitkom put it at 12 billion kWh (12 TWh) in 2014 and 20 billion kWh in 2024. Germany is Europe’s biggest data-centre market. More than a third of its capacity sits around Frankfurt, which grew up beside the DE-CIX internet exchange and the city’s banks. Germany also has its own rules. Under its Energy Efficiency Act, data centres have had to cover 50% of their electricity with renewable power since 2024, counted over the year, and 100% from 2027. Data centres that open from July 2026 must reuse at least 10% of their energy, for example as heat for buildings. That rises to 20% for those that open from July 2028. Operators must also publish their energy data every year and send it to a federal register. What comes next is uncertain. A study for the economy ministry says German data centres could use about 42 TWh in 2035. The grid regulator plans for about 80 to 115 TWh by 2037, based on projects that companies have reported.
The bigger pictureWorldwide, data centres used about 1.5% of electricity consumption in 2024 (IEA), so Germany’s 4% is well above the world average. Germany’s 21 TWh is about 4.3% of the 485 TWh that all the world’s data centres used in 2025 (Hum’s arithmetic).
Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh. 1 TWh = 1 billion kWh.
- 12 TWh 2014, estimated: Bitkom and Borderstep
- 20 TWh 2024, estimated: Bitkom and Borderstep
- 21 TWh 2025, estimated: about 4% of gross electricity consumption
- 42 TWh 2035, forecast: study for the economy ministry
- 80 TWh 2037, low end: grid regulator’s planning range
- 115 TWh 2037, high end: grid regulator’s planning range
Unit: TWh a year.
What nobody knows yet
- Nobody publishes a metered total for all German data centres. The 21 TWh is an estimate.
- How fast it will grow. Forecasts for the mid-2030s run from about 42 TWh to 115 TWh. The regulator itself says it is doubtful that every reported project will be built.
- How much of it is AI. The strategy says about 15% of German data centres are used for AI or high-performance computing, but gives no electricity figure for them.
- Whether the rules will stay as they are. The government’s strategy says it plans to propose changes to the Energy Efficiency Act in 2026.
- The renewable rule is counted over the year. It does not mean a data centre runs on wind and sun every hour.
Sources (15)
- German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German, giving the Borderstep Institute’s 2025 estimate Estimated
“Der Stromverbrauch für Rechenzentren steigt und beträgt ungefähr 21 TWh (2025). Ihr Anteil am Bruttostromverbrauch liegt bei rund 4 %.”
Quote checked on the page, 14 Nov 2026 - German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German Estimated
“Räumlich sind im Gebiet Frankfurt/Rhein-Main die größten Rechenzentrumskapazitäten in Deutschland verortet (mehr als ein Drittel der nationalen Gesamtkapazität; Borderstep, 2025), wobei dieses historisch zunächst wegen der Nähe zum DE-CIX sowie dem dortigen Bankenstandort entstandene und in der EU bedeutendste Cluster”
Quote checked on the page, 14 Nov 2026 - German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German Estimated
“Deutschland ist gemessen an Kapazitäten und Anzahl der Standorte der größte Rechenzentrumsmarkt in Europa.”
Quote checked on the page, 14 Nov 2026 - German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German Estimated
“Der Anteil von Rechenzentren, die in Deutschland für High-Performance-Computing (HPC) oder … genutzt werden, liegt laut Borderstep (2025) bei 15%”
Quote checked on the page, 14 Nov 2026 - German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German Rule or law
“Die Bundesregierung wird Vorschläge für eine Novelle des Energieeffizienzgesetzes (EnEfG) vorlegen, die für 2026 geplant ist.”
Quote checked on the page, 14 Nov 2026 - Germany, Energieeffizienzgesetz (Energy Efficiency Act, EnEfG), official text on gesetze-im-internet.de, in German, § 11 (5) Rule or law
“Betreiber von Rechenzentren decken den Stromverbrauch in ihren Rechenzentren bilanziell 1. ab dem 1. Januar 2024 zu 50 Prozent durch Strom aus erneuerbaren Energien und 2. ab dem 1. Januar 2027 zu 100 Prozent durch Strom aus erneuerbaren Energien.”
Quote checked on the page, 14 Nov 2026 - Germany, Energieeffizienzgesetz (Energy Efficiency Act, EnEfG), official text on gesetze-im-internet.de, in German, § 11 (2) Rule or law
“Rechenzentren, die ab dem 1. Juli 2026 den Betrieb aufnehmen, sind so zu errichten und zu betreiben, dass sie … von mindestens 10 Prozent aufweisen; Rechenzentren, die ab dem 1. Juli 2027 den Betrieb aufnehmen, müssen einen geplanten Anteil an wiederverwendeter Energie von mindestens 15 Prozent aufweisen; Rechenzentren, die ab dem 1. Juli 2028 den Betrieb aufnehmen, müssen einen geplanten Anteil an wiederverwendeter Energie von mindestens 20 Prozent aufweisen.”
Quote checked on the page, 14 Nov 2026 - Germany, Energieeffizienzgesetz (Energy Efficiency Act, EnEfG), official text on gesetze-im-internet.de, in German, § 14 Rule or law
“Die Bundesregierung errichtet ein Energieeffizienzregister für Rechenzentren, in dem die von den Rechenzentren nach § 13 Absatz 1 in Verbindung mit Anlage 3 übermittelten Informationen gespeichert und in eine europäische Datenbank über Rechenzentren übertragen werden.”
Quote checked on the page, 14 Nov 2026 - Germany, Energieeffizienzgesetz (Energy Efficiency Act, EnEfG), official text on gesetze-im-internet.de, in German, § 13 (1) Rule or law
“Betreiber von Rechenzentren sind verpflichtet, bis zum Ablauf des 31. März eines jeden Jahres Informationen über ihr Rechenzentrum nach Maßgabe der Anlage 3 für das vorangegangene Kalenderjahr zu veröffentlichen und an den Bund zu übermitteln.”
Quote checked on the page, 14 Nov 2026 - Bundesnetzagentur (Germany’s grid regulator), approval of the scenario framework for the electricity grid development plan 2025-2037/2045, April 2025, in German Forecast
“Dadurch ergibt sich ein zusätzlicher Stromverbrauch durch Rechenzentren zwischen ca. 80 und 115 TWh und damit mehr als im Entwurf der Übertragungsnetzbetreiber.”
Quote checked on the page, 14 Nov 2026 - Bundesnetzagentur (Germany’s grid regulator), approval of the scenario framework for the electricity grid development plan 2025-2037/2045, April 2025, in German Forecast
“Ob alle Projekte mit den gemeldeten Anschlussleistungen realisiert werden, kann bezweifelt werden.”
Quote checked on the page, 14 Nov 2026 - German Federal Government, answer to a parliamentary question, Bundestag Drucksache 21/1263 (18 August 2025), in German Forecast
“Ein Gutachten des Bundesministeriums für Wirtschaft und Energie (BMWE) schätzt, dass der Stromverbrauch aller Rechenzentren in Deutschland im Jahr 2035 bei ca. 42 TWh pro Jahr liegen könnte.”
Quote checked on the page, 14 Nov 2026 - Bitkom (German digital industry association), press release on its data-centre study with the Borderstep Institute (21 November 2024), in German; 1 Mrd. kWh is 1 TWh Estimated
“Er wird 2024 bei 20 Mrd. Kilowattstunden liegen – 2014 waren es noch 12 Mrd. kWh.”
Quote checked on the page, 14 Nov 2026 - IEA, Energy and AI (2025) Estimated
“Data centres accounted for around 1.5% of the world’s electricity consumption in 2024, or 415 terawatt-hours (TWh).”
Quote checked on the page, 3 Oct 2026 - IEA, Key Questions on Energy and AI (2026) Estimated
“electricity consumption from data centres roughly doubling from 485 TWh in 2025 to 950 TWh in 2030”
Quote checked on the page, 3 Oct 2026
Hum’s sums
- 21 TWh ÷ 485 TWh = about 4.3% of the world’s data-centre electricity (2025)
Cite this
German Federal Government, Rechenzentrumsstrategie (national data-centre strategy), adopted March 2026, in German, giving the Borderstep Institute’s 2025 estimate, as quoted in Hum, “How much of Germany’s electricity do data centres use?”, https://humearth.org/q/germany (quote checked 14 Nov 2026).
Cite the original source first; Hum is where you found it.
What do Wh, kWh and TWh mean?
Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh, and 1 TWh = 1 billion kWh. Hum compares each number with something everyday so you don’t need the units.
Send this answer
Data centres use about 4% of Germany’s electricity: about 21 TWh in 2025. More than a third of the capacity is around Frankfurt.