The world's data centres already use as much electricity as a country. AI is the fastest-growing part.

2025: about 485 terawatt-hours a year.
2025 · single published estimate (IEA)

In 2025 they used about 485 TWh, more than France uses in a year. The IEA expects about 950 TWh by 2030, close to Japan's 1,027.

2025
See the data

A country lights up when data centres use more electricity in a year than it does (middle figure). The speaker button plays the hum: louder as they use more, wavering in forecast years. Glows are the biggest data-centre hubs, sized by power capacity. Data centres: IEA, Energy and AI (2025) and its 2026 update. Countries: Ember (2025). How we know

Side by side in 2025

Data centres against whole countries, in electricity a year. The year above moves this too. Dashed means calculated; dim means forecast.

  1. RussiaRussia: 1,178 TWh
  2. JapanJapan: 1,027 TWh
  3. CanadaCanada: 654 TWh
  4. GermanyGermany: 517 TWh
  5. Data centresData centres: 485 TWh, of which AI about 26.5 to 38%
  6. FranceFrance: 481 TWh
  7. United KingdomUnited Kingdom: 312 TWh
  8. NetherlandsNetherlands: 121 TWh

AI's part, about 26.5–38%: the United States' share, used as a world estimate.

Where it's heading

The IEA's main forecast almost doubles data-centre electricity by 2030. Its scenarios for 2035 span 700 to 1,700 TWh, so we show all of it. The bright line is measured; the dim range hasn't happened yet.

Data-centre electricity, measured and forecast05001,0001,5002,000TWh20172020202520302035JapanGermanyFrancetoday 485
2017–2023: Calculated back from 2024 at about 12% growth a year (dashed). Country lines show each country's electricity use in 2025. Every year, and how we got it

Where the electricity goes

Of the 485 TWh the world's data centres used in 2025, AI was about 129 to 184 TWh: roughly a quarter to two-fifths. The rest runs everything else online: streaming, cloud storage, websites, email and business software.

AI: 26.5%–38%Everything else

AI's share is a figure for the United States, used as a world estimate, because nobody publishes a world figure in words. How we know

AI is the fastest-growing part

Electricity growth in 2025. AI-focused: IEA, Key Questions on Energy and AI (2026). All data centres: calculated from 415 TWh in 2024 to 485 TWh in 2025.

What it does to the world

Three effects have published worldwide numbers (MEASURED). Others are real but only known place by place, so instead of inventing a total we explain them with named cases (EXPLAINED).

MEASURED

Electricity

485 TWh a year

Published for 2025 (IEA). Forecast for 2035: 700 · 1,200 · 1,700 TWh.

MEASURED

CO2 from that electricity

180 Mt CO2 a year

Published for 2024 (IEA). Forecast for 2035: – · 350 · 500 Mt (no low case published).

MEASURED

Water

0.12 · 2.54 · 5.48 litres per kWh

Cooling at the building uses 0.12 · 0.36 · 1.08 litres per kWh; the power plants feeding it often use more: 0 · 2.18 · 4.4 litres per kWh. For 2025's electricity that comes to 58.2 · 1,232 · 2,658 billion litres (calculated).

EXPLAINED

Strain on the grid

Ireland and the eastern United States

In Ireland, data centres used 22% of all metered electricity in 2024, up from 5% in 2015. In the eastern US, a 5,250 MW increase in the PJM grid's demand forecast, almost entirely from data centres, helped drive the results of its latest capacity auction.

Sources: Central Statistics Office Ireland, 10 June 2025 · Utility Dive, 18 December 2025

Read the quotes
  • The percentage share of metered electricity consumption used by data centres rose to 22% in 2024 from 5% in 2015
    Central Statistics Office Ireland, 10 June 2025
  • In part, the latest auction results were driven by a 5,250-MW increase in PJM's demand forecast — almost entirely driven by data centers
    Utility Dive, 18 December 2025
EXPLAINED

Local air

Memphis, Tennessee

In Memphis, the county's permit lets xAI operate 15 generators at its data centre, up to 247 megawatts; TechCrunch describes them as natural gas generators. According to their manufacturer, the turbines emit nitrogen oxides, a key contributor to smog, and formaldehyde.

Sources: TechCrunch, 3 July 2025, ‘xAI gets permits for 15 natural gas generators at Memphis data center’ · NBC News, 17 June 2025

Read the quotes
  • The permit issued by the Shelby County Health Department says that xAI can operate 15 Solar SMT-130 generators with certain emissions controls, which can generate up to 247 megawatts.
    TechCrunch, 3 July 2025, ‘xAI gets permits for 15 natural gas generators at Memphis data center’
  • The turbines emit nitrogen oxides, a key contributor to smog, and formaldehyde, among other pollutants, according to their manufacturer.
    NBC News, 17 June 2025
EXPLAINED

Chips and e-waste

Worldwide

A peer-reviewed study of generative AI's e-waste finds it could potentially reach 1.2 to 5.0 million tons in total over 2020 to 2030.

Source: Nature Computational Science, 28 October 2024, ‘E-waste challenges of generative artificial intelligence’

Read the quote
  • this e-waste stream could increase, potentially reaching a total accumulation of 1.2–5.0 million tons during 2020–2030
    Nature Computational Science, 28 October 2024, ‘E-waste challenges of generative artificial intelligence’
EXPLAINED

Land

Prince William County, Virginia

The planned Digital Gateway would span 34 buildings and 1.7 gigawatts of data-centre capacity on 2,139 acres near Manassas National Battlefield; WTOP reported it would be the largest data-centre corridor in the world. A court found the county's advertised notice did not comply with either the state or county code.

Sources: Bisnow, 8 April 2026 · WTOP, 9 August 2025 · WTOP, 9 August 2025, quoting the court

Read the quotes
  • Within the 2,139-acre Digital Gateway, Blackstone subsidiary QTS and Compass Datacenters have planned to develop large data center campuses that at full build-out would span 34 buildings, 22M SF and 1.7 gigawatts of capacity.
    Bisnow, 8 April 2026
  • would be the largest data center corridor in the world, with 37 data centers spread out across over 2,100 acres in western Prince William, near Manassas National Battlefield
    WTOP, 9 August 2025
  • This Court finds that the advertised notice provided by the County did not comply with either the State or County code.
    WTOP, 9 August 2025, quoting the court
EXPLAINED

Noise

Chandler, Arizona and Prince William County, Virginia

Residents near data centres in Prince William County say the constant drone, especially at night, causes anxiety and deprives them of sleep. Chandler, Arizona requires data centres to be built so their sound doesn't exceed the background level measured in a baseline study.

Sources: Prince William Times, 27 February 2023 · City of Chandler, Ordinance No. 5033, 8 December 2022

Read the quotes
  • But residents say the constant drone, especially at night, causes anxiety and deprives them of sleep.
    Prince William Times, 27 February 2023
  • The Data Center must be designed and built to incorporate sound mitigation methods sufficient to prevent the sound levels emanating from the Data Center ... from exceeding the ambient noise levels that were observed in the baseline study.
    City of Chandler, Ordinance No. 5033, 8 December 2022

Every source, and how each range was built, is on How we know.

Your part

Your typing is small. Your video isn't. And your voice is the big one.

Electricity141 Wh a weekfrom 60.8 to 1,213Electricity: 60.8 · 141 · 1,213 Wh a week
CO266.8 g CO2 a weekfrom 7.6 to 679CO2: 7.6 · 66.8 · 679 g CO2 a week
Water0.359 litres a weekfrom 0.00729 to 6.65Water: 0.00729 · 0.359 · 6.65 litres a week

Your questions: 47.6 Wh. Your pictures: 3.66 Wh. Your videos: 90 Wh, 64% of your week.

Low · middle · high, from the figures on How we know. One week, everything counted at the data centre (not your phone).

What actually reduces it

Your week from Your part, ranked: what each change would save, in watt-hours a week. Same scale for every bar, so the small ones look as small as they are.

  1. Skip your one short AI video90 Wh 25.3 to 944: saves about 90 Wh (25.3 to 944) a week
  2. Take one day a week off AI20.2 Wh 8.68 to 173: saves about 20.2 Wh (8.68 to 173) a week
  3. Ask 5 fewer questions a day11.9 Wh 8.4 to 65.1: saves about 11.9 Wh (8.4 to 65.1) a week
  4. Make 2 fewer AI pictures a week2.44 Wh 1.26 to 5.8: saves about 2.44 Wh (1.26 to 5.8) a week

Middle figure, with the low to high range. Per-use figures from How we know, counted at the data centre.

Bigger than any of these

Next to the world's total, one person's week is tiny. The biggest levers aren't in your chat window:

Claims to read twice

When a company says its AI is green, these are the common ways the wording can say more than the electricity does. They're practices, not accusations: each one is explained by researchers, regulators or reporters.