How much of Brazil’s electricity do data centres use?
Short answerAbout 1.7% in 2024, by an industry estimate.
About 1.7% of Brazil’s electricity consumption in 2024, by an estimate from Brasscom, the country’s tech industry association. That is 11.3 TWh out of 650.4 TWh. It is a calculation, not a count from meters, and there is no official figure for today. Brazil’s Energy Research Office (EPE) plans the country’s energy with the government, and it publishes forecasts. In its plan to 2036, data centres use 30 TWh a year by 2036. That would be about 3.1% of the 979 TWh Brazil is forecast to use that year (Hum’s arithmetic). EPE calls data centres the main driver of growth in electricity use by shops and services. Its chart of big new loads shows data centres at 3 TWh in 2026, so its forecast is a rise of about 10 times in ten years. EPE says requests from data-centre projects to connect to the main grid went up in 2025. It also says the real growth will depend on how fast the planned investments happen. In September 2026 Brazil passed a law called Redata that gives data centres tax breaks. To qualify, a data centre must cover all of its electricity demand with renewable or low-emission sources. It must also use no more than five hundredths of a litre of water per kWh, checked every year.
The bigger pictureWorldwide, data centres used about 1.5% of electricity consumption in 2024 (IEA). If the industry estimate is right, Brazil’s 1.7% is close to the world average.
Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh. 1 TWh = 1 billion kWh.
Why the claim misleads
EPE says Brazil’s electricity is among the most renewable in the world. That draws data-centre companies that want clean power, and the Redata law is meant to draw more.
What nobody knows yet
- How much Brazil’s data centres use today. Brasscom works its figure out from installed computing power, an efficiency factor and time, not from meters. If the machines don’t run at full power all year, the real figure is lower.
- EPE’s chart shows only 3 TWh for data centres in 2026, about 0.4% of the 702 TWh Brazil is forecast to use that year. That is far below Brasscom’s figure. EPE’s chart is about large data centres, so the two may not count the same things.
- How fast it will grow. The 30 TWh for 2036 is a forecast, and EPE says it depends on investments that have not been made yet.
- How the Redata rules will work in practice. The law leaves the details of the clean-power rule to regulations.
- How much of it is AI. Nobody publishes that for Brazil.
Sources (13)
- Brasscom (Brazil’s tech industry association), study of energy and water use in Brazil’s data centres, August 2025, in Portuguese; total consumption taken from EPE’s national energy balance Estimated
“DATA CENTERS REPRESENTAM 1,7% DO TOTAL CONSUMIDO ( 11,3 TWh )”
Quote checked on the page, 15 Nov 2026 - Brasscom (Brazil’s tech industry association), study of energy and water use in Brazil’s data centres, August 2025, in Portuguese; total consumption taken from EPE’s national energy balance Estimated
“O CONSUMO DE ENERGIA ELÉTRICA NO BRASIL NO ANO DE 2024 FOI DE 650,4 TWh”
Quote checked on the page, 15 Nov 2026 - Brasscom (Brazil’s tech industry association), study of energy and water use in Brazil’s data centres, August 2025, in Portuguese; total consumption taken from EPE’s national energy balance Estimated
“Potência Instalada (TI) no Brasil em 2024: 843,1 MW”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036, energy demand booklet, October 2026, in Portuguese Forecast
“Em 2036, os data centers responderão por 30 TWh do consumo de eletricidade do setor de serviços.”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036 (ten-year energy plan), summary report, October 2026, in Portuguese; table 2-4, columns 2026, 2031 and 2036 Forecast
“Consumo total de eletricidade (TWh) 702 846 979”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036 (ten-year energy plan), summary report, October 2026, in Portuguese Forecast
“os data centers se destacam como o principal vetor de crescimento do setor de comércio e serviços”
Quote checked on the page, 15 Nov 2026 - Cenário Energia (Brazilian energy news site), report on EPE’s PDE 2036, 10 November 2026, in Portuguese; the two figures are the chart labels in EPE’s energy demand booklet News report
“a demanda elétrica dos data centers saltará de 3 TWh em 2026 para 30 TWh em 2036”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036, energy demand booklet, October 2026, in Portuguese Measured
“Em 2025, observou-se aumento dos pedidos de acesso à rede básica por projetos de data centers”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036, energy demand booklet, October 2026, in Portuguese Forecast
“A expansão efetiva da participação dessas grandes cargas dependerá do ritmo de concretização dos investimentos previstos”
Quote checked on the page, 15 Nov 2026 - EPE (Brazil’s Energy Research Office) and Ministry of Mines and Energy, Plano Decenal de Expansão de Energia 2036 (ten-year energy plan), summary report, October 2026, in Portuguese Forecast
“reforçando a posição do Brasil entre os países com as matrizes elétricas mais renováveis do mundo”
Quote checked on the page, 15 Nov 2026 - Brazil, Lei nº 15.504 of 15 September 2026 (the Redata data-centre tax regime), text on the Federal Senate’s legislation site, in Portuguese Rule or law
“atender à totalidade da sua demanda de energia elétrica por meio de contratos de suprimento ou autoprodução proveniente de geração a partir de fontes renováveis ou de baixa emissão, na forma de regulamento”
Quote checked on the page, 15 Nov 2026 - Brazil, Lei nº 15.504 of 15 September 2026 (the Redata data-centre tax regime), text on the Federal Senate’s legislation site, in Portuguese Rule or law
“igual ou inferior a 0,05 L/kWh (cinco centésimos de litro por quilowatt-hora), com aferição anual”
Quote checked on the page, 15 Nov 2026 - IEA, Energy and AI (2025) Estimated
“Data centres accounted for around 1.5% of the world’s electricity consumption in 2024, or 415 terawatt-hours (TWh).”
Quote checked on the page, 3 Oct 2026
Hum’s sums
- Brasscom writes decimals with a comma: 1,7% is 1.7%, 11,3 TWh is 11.3 TWh and 650,4 TWh is 650.4 TWh. Check: 11.3 ÷ 650.4 = about 1.7%
- 30 TWh ÷ 979 TWh = about 3.1% of the electricity Brazil is forecast to use in 2036
- 3 TWh ÷ 702 TWh = about 0.4% of the electricity Brazil is forecast to use in 2026
- 30 TWh ÷ 3 TWh = 10 times
Cite this
Brasscom (Brazil’s tech industry association), study of energy and water use in Brazil’s data centres, August 2025, in Portuguese; total consumption taken from EPE’s national energy balance, as quoted in Hum, “How much of Brazil’s electricity do data centres use?”, https://humearth.org/q/brazil (quote checked 15 Nov 2026).
Cite the original source first; Hum is where you found it.
What do Wh, kWh and TWh mean?
Wh is a watt-hour: a 1-watt light left on for an hour. 1 kWh = 1,000 Wh, and 1 TWh = 1 billion kWh. Hum compares each number with something everyday so you don’t need the units.